Monthly Archives: March 2014

Air tightness test

When the facade comes to an end a air tightness test must be done to assure that the envelope is closed. As this project is BBC & HQE it has many constraints and for example only the tolerance of 1m3 of air flow for the test done at 4 Pa for the surface of 190m². This test is done in depression. The gas is spread at exterior for the measurements and since the volume is in depression the volume of gas entered in the test room is observed from inside. Because the flow of the wind at 50Pa is noticebale this test is done starting from this point for varying pressure in the difference of 10 Pa that means at 50Pa, 40Pa, 30Pa, 20Pa and 10Pa. The result obtained is extrapolated for 4Pa as required by the french laws to find the volume of air entered in the envelope. However generally in Europe the value at 10Pa is accepted.

Below are some photos of this test.
20140224_142813

20140224_144640

During explanation of the procedures of test and objective:

20140224_144654

From the test done, it is obtained 1.9m3 which is almost double then the target. So the thermal bridge has to be identified in order to treat for efficiency of the building envelope.

20140224_145922

20140224_150029

20140224_150038

20140224_150100

20140224_150236

20140224_150334

20140224_150544

20140224_150623

20140224_150702

20140224_150742

20140224_151003

20140224_151134

20140224_151207

20140224_151943

20140224_151958

20140224_152159

20140224_152530

20140224_153713

A high volume of air transfer was found across the concrete bloc, concrete blocs are very weak insulator.

20140224_153731

Also the reservations for wire are also reasons for the air circulation, so the reservations must be enclosed properly to avoid the air transfer.
20140224_153941

20140224_154054

20140224_162036

20140224_162039
As the windows covered maximum of surface areas and a remarkable air transfer is observed from wondows. A treatement has to be done for these windows and test must be done in order to obtain the objective desired (minimum : 1m3 )

Facades implantation

As the objective of project is to gain title of “high quality environmental” and “low energy consummation” there are many constraints since the conception till the end of the project. The façade in this project is of aluminium triple glasses and the blocs made by cement and glass. This facade is done in two phases. In the first phase the aluminium blocs with triple glasses layer is implanted. These blocs are fabricated in the factory and it is placed using the fixing lugs. When the airtight/watertight is done then the blocs made by cement and glass (composite ciment verre; CCV) is implanted. As I explained in the previous topics the medium of implantation of facade is bi-mâts, a motorized platform of work standing in two metallic pillars.

20140313_101537

Phase I
In the first phase the prefabricated aluminium blocs are implanted in the fixing lugs prepared for this. The fixing lugs must be on the appropriate height and the escapement between them must be correct as the blocs are prefabricated. The position of those blocs are found by the geometrical lines drawn in the project and the need of the blocs. However a adjusting screw is integrated on the lugs for the simplicity of the adjustment.
20140226_133639

The blocs are either implanted by the work platform, nacelle or by using crane.
20140313_145302

20131220_094116

20131220_094130

20140114_152856

pattes

These blocs are fixed with angles at corners to made airtight and watertight. The small openings are then closed by silicon. windows are then put in place and finishing touch of facades is done.
20140203_142131

20140203_142110

20140212_161022

If the blocs are implanted with accuracy the second phase starts:

Phase II

For the second phase the platform is adjusted to leave enough space to implant CCV shells. These blocs are also prefabricated and implanted in the same way as aluminium blocs. First the fixing lugs are implanted with accuracy and the implantation starts.

20140121_084400

The pillars must be isolated to avoid the thermal bridge.
20140213_165121

Once the blocs are implanted, the adjust must be done to have the predefined spacing between them. Below are some photos before adjusting.

20140311_132915

20140311_133008

Once the blocs are properly fixed the curtain is fixed on the openings left for this purpose. Then the finishing touch is given to have the good finishing of the facade.

point supp de fixation

20140130_133644

façade Garnier

façade, du pont

Impermeability(Water tightness) test

When the surface is treated for impermeability to be sure that is really impermeable a test of impermeability of water is mandatory. For this purpose the water exit are closed temporarily and the water of sufficient height is put for the test. the filled water is colored with florescence powder in order to verify if the infiltration viewed is from the the surface in test.

Add of florescence for the test:
20140311_144514
20140311_144838
20140311_151330
20140306_161813

This water remains for some day and then the control of impermeable is done. In the control the company who treated the surface is present along with the construction company and the member of sub-contractors for garden etc.

If the infiltration is observed then the sub-contractor company who treated the impermeability finds the area of infiltration and it treats the surface.

20140205_143902

20140205_151344

20140205_151616

20140313_135332

Then retest is done in the same way with the another florescence color to verify the infiltration. If the surface is impermeable the verbal process of receiving support is delivered to the executing company by the sub-contractor who treats the surface.

Neuilly - Plan mise en eau

click here for the sample of process verbal of support reception

Making of a “Garden”

In this topic I am going to describe how the modern garden is made when there exist a building compartiment underneath. For the plane garden there must be no problem for the level of soil. But in this project we have a discontinous surface as in picture below.

20131218_113706

I’l talk later ways to overcome this uncontinuous surface. In order to make the garden firt we applied the DELTERAXX just above the concrete surface already treated for impermeability, this material permits infiltration of water from on side (top) and is impermeable the other side (bottom). The water can go down and flow to the exit point.

20140205_105338
20140313_100852

20140205_105401

Then extruded polystyrene (polystyrène extrudé ) is put on to gain the height of the soil which is quite expensive for quality soil as in the photos:

20140219_092021

It is then covered by thin layer partly permeable to leave only the water to infiltrate and to resist the solid materials this is geotextile materials.

20140205_105536

Knowing the exact position of plant the two bed of iron bars are kept just below the plant in order to fix the plant with the ground.

image (1)

When all these prepartion are made, the soil is put from above to an predefined height.
20140213_165452

20140313_14055820140313_140645

In order to hold the trees properly welded two layers of iron bars (square) of dimension 2mX2m are posed where there are plants. Then the plants are planted.
20140228_105149

tree
tree1

20140228_104157
20140306_144700

jardin 1

jardin
jardin2